Car Park Trafficable System

The Orchards Retirement Apartments

ArchitectArcline Architecture
ContractorAspec Construction
Size500m2
Specification1 X 10mm of Mastic Asphalt roofing Topped with 30mm of Mastic Asphalt paving
Year2015

Scope

The client was looking for a robust system that would protect the floor below and was looking for a hard wearing surface which was waterproof The product had to be durable, strong and flexible enough to handle some movement within todays modern structures.

Solution

As the project would be staged to allow construction to progress the upstand details were all carried out first to allow cladding to be installed and Gib Boarding to be carried out.

Asphaltech and their qualified tradesmen worked on this project with limited space and movement during the later stages of the construction project.

A complete QA package was handed over to the client at the end of the project showing sign off sheets and pictures during construction.

"George Griffiths personally supervises his small team, who all work to highly professional standards ensuring that the exacting detailing required by the Museum's heritage architects is always met or exceeded. "
JOHN GLEN, Auckland Museum Facilities Manager // AUCKLAND WAR MEMORIAL MUSEUM
"Mastic asphalt has a long life span of 60 years (source RICS). Fully recyclable, it has a low impact on the environment. Benefits of mastic asphalt are its durable, waterproof, voidless and self compacting."
Pure Asphalt Company Limited – UK